A utility contractor needed Network Rail to accept two new 11 kV circuits crossing a bridge above an operational London station.
The challenge. The circuits were to run across a road bridge spanning platforms, track, and signalling and telecoms cables. Network Rail needs evidence that new HV cables will not interfere with train detection, signalling or communications, and a short statement that the risk is low is not enough. The contractor needed a calculation-based assessment that would be accepted first time.
What we did. We carried out a desk-based EMF and EMC assessment, with no site visit needed. We modelled the 50 Hz magnetic fields from both circuits at their full rated current of 418 A, far above the expected load. We compared the results with the CEMFAW Action Level of 1000 µT and the public Reference Level of 100 µT. We then assessed the risk to track circuits, signalling and telecoms cables against the EN 50121 railway EMC standards. Comparative modelling showed that laying the cables in trefoil cut the external field by more than ten times compared with single cores laid flat.

The outcome. Even at full rated current, the field 60 cm from the cables was below the 100 µT public Reference Level. At the railway assets, 4 m or more below, it fell to under 1 µT, and induced voltages in railway cables were in the microvolt range. No mitigation was needed, Network Rail accepted the report without comment, and the installation went ahead.